How long does a multiplex take, from first sketch to move-in?

Newly framed wood walls with diagonal bracing standing on a plywood subfloor, offcuts of lumber on the deck and a brick building behind a fence in the background

The most common question we hear after "how many homes can I build?" is "how long will it take?" The honest answer is about two years from first sketch to move-in for a typical multiplex, which is the span our New Westminster and Burnaby multiplex guides use. Neither City publishes a guaranteed processing time, so this post doesn't invent one. Instead, it walks through each stage, shows what controls its pace, and points out the places where projects lose months.

The short version

StageWhat sets the pace
1. Lot checkHow fast you can confirm zone, lane, trees, slope, title and servicing.
2. DesignYour designer's schedule and how many times the plans change.
3. Pre-approvalsEngineering review, tree permits and early talks with the electrical utility.
4. PermitsCompleteness of the application and how many rounds of comments come back.
5. ConstructionWeather, trades, inspections and the electrical connection.
6. OccupancyFinal inspection, finished landscaping and trees.

Stage 1: check the lot before you pay for drawings

Everything downstream depends on facts about the lot. Burnaby's own step-by-step guide to new home construction starts here: confirm zoning and site constraints on BurnabyMap, including streamside protection, heritage, archaeology, underground storage tanks and covenants on title. New Westminster's Infill Housing Program guide says the same thing in its own words, and adds that you should assess servicing costs early, because infill is "a more intensive use than a single detached house."

This stage is where a few days of checking can save months. A covenant or a protected tree found after design is finished means redesigning. Our lot map is a quick first look, and our posts on Burnaby's tree bylaw and New West servicing costs cover two of the most common surprises.

Stage 2: design

Design time depends on your designer and on how settled your plans are. Two things can help:

  • Pre-made plans. Burnaby's Housing Design Library is an online gallery of designs reviewed against the R1 zone. The City is clear that using one doesn't guarantee approval or earn faster review: each still needs a full building permit application.
  • Checking against the zone as you go. Burnaby's AI PreCheck tool reviews plans against more than 50 rules in the Zoning Bylaw and returns a report within 2 business days. It's optional, and the City says the report is not an approval. It can catch a setback or height problem before a plan checker does.

The biggest design delay is changing your mind. Decide early whether you're building to sell, to rent, or to keep a unit for yourself, because that drives the layout.

Stage 3: pre-approvals, which many owners don't expect

Both cities want certain reviews done before or alongside the main application.

  • Burnaby: you need Engineering pre-application approval before you submit the building permit. The City says complete submissions typically take about 15 business days to review. The same guide lists tree protection, BC Hydro electrical capacity, stratification and waste collection as things to plan for at this stage.
  • New Westminster: before the Development Permit application, you submit a Utilities Modeling Analysis application to Engineering and include the fee slip with your Development Permit. A Tree Permit application must go in at the same time as the Development Permit, even if there are no protected trees on the lot.

Start the electrical conversation here too. BC Hydro (Burnaby) doesn't publish a standard timeline for design projects; its page says the design team gives an estimated timeline once all factors are known, and that work needing outages to other customers typically adds 15 working days. New Westminster runs its own electrical utility, so check capacity with the City early. Our post on Hydro upgrade costs explains why this item can be small or very large.

Stage 4: permits

This is where the two cities differ most.

Burnaby. If the design fits the R1 zone, there's no rezoning and no public hearing; it goes to a building permit. You apply through the My Permits Portal with the checklist for your building type, and full fees are due when you apply. Staff review the application and send deficiency lists, and the permit issues only once every requirement is met and fees are paid. Burnaby says wait times depend on the volume of applications and the project's complexity. Development cost charges are collected when the permit issues. If there's an existing house, you also need a demolition permit, which requires a waste diversion plan.

New Westminster. RGO-A and RGO-B lots need two permits in sequence. First, a Development Permit, reviewed against the City's ground-oriented infill design guidelines. The City assigns a Planning File Manager, refers the file internally and sometimes externally, asks for resubmission if issues remain, then forwards it to the Director of Planning and Development to consider issuing it. The guide says incomplete applications won't be accepted. Second, the building permit. Before it issues, you sign a Works and Services Agreement backed by security, such as a letter of credit. A registered architect is required for buildings of 600 m² or more, or with 5 or more homes.

In both cities, each round of comments costs time, so a complete, well-checked application is the part of the permit clock you control most.

Stage 5: construction and inspections

Once the permit is in hand, construction runs through demolition, excavation, foundation, framing, roofing, mechanical, electrical, insulation, drywall and finishes. Trade permits come from licensed sub-trades, and Burnaby requires 24 hours' notice to book inspections.

The electrical connection is often the last external dependency. BC Hydro's process ends with your electrician's authorization and permits, then a site inspection, meters and energization. On a multiplex, permanent meters go in as individual units are ready.

Stage 6: occupancy

In Burnaby, nobody moves in until the project passes its final building inspection and receives an Occupancy Certificate, and the City notes trees must be planted before that final inspection. In New Westminster, the landscape deposit taken at the Development Permit stage is refunded after the City inspects the landscaping. Leave room in the schedule for landscaping; it's easy to treat as an afterthought.

What you can do to keep it moving

  • Check the lot before hiring a designer.
  • Start the electrical and servicing conversations during design, not after.
  • Submit complete applications. In New West, incomplete ones aren't accepted; in Burnaby, they come back as deficiency lists.
  • Lock the design before you apply. Changes after submission restart parts of the review.
  • Budget for carrying costs over the full two years, not just the build months.

Why timing matters more this year

The incoming B.C. government has said it plans to repeal the provincial multiplex law, which we covered in our news post. Nothing has changed in either city's zoning yet, and both bylaws stay in force until a council amends them. But if you're weighing whether to start now, the stages above are the clock you'd be racing. If you'd rather not run that clock yourself, selling with plans or permits or selling to a builder may suit you better.

Not sure where your lot stands? Request a free lot review and we'll check the zone, servicing and constraints that set your timeline.