Construction-only vs all-in: how to compare multiplex builder quotes

Aerial view of a construction site with wood foundation forms set out over gravel, lumber stacked inside and plastic sheeting on the soil

You've asked three builders to price a fourplex or sixplex, and the numbers come back far apart. The lowest one is tempting. Before you pick it, check that the three quotes are pricing the same job. Very often they aren't: one is a construction-only number, one includes design and permits, and one is a true all-in budget. This post gives you a simple way to line them up so you're comparing like with like.

For the zoning side of the project, start with our Burnaby multiplex guide or the New Westminster multiplex guide. This post is about the money.

Why the gap is so large

By Design Construction sees duplex and multiplex construction at about $275 to $500 or more per square foot, excluding land, plus a 10 to 15% contingency. Its experience is that a construction-only quote can look about 40% cheaper than an all-in budget for the same building. The gap is everything outside the build itself: design, engineering, permits, City charges, utility connections, financing and the cushion for surprises.

BC Housing's consumer guide to hiring a builder puts it plainly: "One-page quotes do not provide enough information to make an informed decision." The guide says a proper estimate should cover materials, labour, equipment, taxes, professional services and contingencies.

Step 1: build a comparison table

Put every quote into the same table, one row per cost item. Where a quote doesn't mention an item, write "not included" rather than leaving it blank. Blanks are where the surprises live.

Cost itemWhat to ask
Design and engineeringArchitect or designer, structural, geotechnical, energy modelling, surveys. Included, or billed separately?
PermitsWho applies, and who pays the building permit and plan review fees?
Demolition and site prepRemoval of the old house, hazardous materials testing, tree work, excavation and haul-away.
City servicingNew water, sewer and storm connections and any frontage works the City requires.
Development and amenity chargesCharged per new home. Usually not in a builder's price.
Electrical serviceBC Hydro (Burnaby) or New Westminster's own electric utility: the upgrade on the utility side and the work on your side.
ConstructionFoundation to finishes, with a specification list, not just a total.
AllowancesDollar amounts set aside for items not yet chosen, like cabinets, flooring and fixtures.
Landscaping and pavingRequired landscaping, paths, fire access path, parking pad.
Warranty, insurance and feesHome warranty enrolment, builder's risk insurance, the builder's fee or margin.
GSTIs the price before or after GST?
ContingencyIs there one, how big, and who controls it?

Two rows on that list are site-specific and can swing the budget the most. We've covered both in detail: why a Hydro upgrade can cost $2,000 or $120,000, and what Burnaby's development cost charges add per home. In New Westminster, see who pays for water and sewer upgrades.

Step 2: check the GST line

This one catches people. The Canada Revenue Agency says a GST-registered contractor hired to build a home on land you own must charge GST on the labour and materials it provides. You may qualify for a GST/HST new housing rebate, but you apply for it yourself; the contractor can't apply for it or credit it to you. If one quote is "plus GST" and another includes it, the 5% difference alone can make the cheaper quote look cheaper than it is. Tax on a multiplex you plan to sell or rent can get complicated, so talk to an accountant before you sign.

Step 3: understand the type of price

BC Housing's guide describes the main contract types, and they carry risk differently:

  • Fixed price. One price set up front. The guide notes these are usually used for very small, simple projects, and quality standards need to be well defined. On a multiplex, read what's excluded as carefully as the price.
  • Cost-plus. The builder charges for materials, labour and expenses plus a management fee, often a percentage of cost. The contract has to define what counts as "cost." The guide warns that if you buy materials yourself, the builder may still charge its fee on them.
  • Construction manager. An hourly or fee-based manager runs the job while you hold the trade contracts. Responsibilities and risk shift toward you, so understand them before you choose this route.

A low fixed price with large allowances and a long exclusions list can end up costing more than a higher cost-plus estimate with realistic numbers.

Step 4: match the quote to the stage of design

The guide explains that estimates firm up as the project does: rough at first, more detailed once there are plans, and final once the building permit is issued. A quote given from a sketch is a ballpark, not a price. If one builder priced from full drawings and another from a site visit, their numbers aren't comparable yet. Give every builder the same drawings and the same specification list, then ask again.

Step 5: check the builder, not just the number

  • Licence. New homes in B.C. need a licensed residential builder. Look the company up on BC Housing's Public Registry of Licensed Residential Builders and check that the name on the contract matches the name on the licence. You can't act as an owner builder on a multiplex; we explain why in partnering with a builder.
  • Warranty. BC Housing says builders must arrange third-party home warranty insurance before getting a building permit, and the minimum 2-5-10 coverage can't be waived by a side agreement. Ask which warranty provider each builder uses.
  • Holdback. Under the Builders Lien Act, the owner holds back 10% of the amount owing until the work is substantially complete and the holdback period has run out. BC Housing flags a builder who won't discuss holdbacks as a red flag.
  • Change orders. Changes should be in writing, signed by both sides, with the contract saying who can approve them.

A worked example

Say your design is a fourplex with about 3,000 sq ft of floor area. At By Design Construction's range of $275 to $500 or more per square foot, construction alone runs roughly $825,000 to $1.5 million or more. A 10 to 15% contingency on top adds about $82,500 to $225,000. Then come design, permits, City charges, servicing and electrical, which depend on your lot. If a builder quotes $900,000 for "the build," that number may be fair for the building. It just isn't what the project costs you. These are illustrations from published ranges, not quotes.

The takeaway

Don't compare totals. Compare rows. Get every quote onto one table, mark what's missing, put each on the same GST basis, and give every builder the same drawings. The cheapest quote is often the one that leaves the most out.

If you'd rather not take on construction risk at all, selling to a builder or partnering with one may suit you better. Our selling to a builder page compares the options, or request a free lot review and we'll look at what your lot allows first.

Sources

General information, not legal, tax or financial advice. Rules change; confirm anything for your property with the City and qualified professionals.